Wanstead Wildlife |
|||||||||||
|
The Lake System of Wanstead Park - Part 2 |
|||||||||||
|
|||||||||||
Heronry Pond Reprinted (with minor modifications) with acknowledgements to James Berry & Alan Cornish, from their work "The Lake System of Wanstead Park & The Mystery of The Heronry Pond" © James Berry & Alan Cornish, March 1978. Geological data indicated that the north east quarter of Heronry Pond was bounded by Taplow Gravel, whereas the remainder of the lake appeared to be seated directly onto London Clay. Since the latter is impervious to water, it seemed probable that any leakage would occur into the Taplow Gravel, (see geological map - page 9). This posed the question: how deep was the layer of Taplow Gravel adjacent to Heronry Pond? Did the bed of the pond rest on the underlying London Clay, or was there a layer of gravel between the bed of the lake, and the underlying clay? In order to gain information on this point, geological survey specialists were contacted early in 1975. Albury Laboratories Site Investigation Ltd., kindly undertook to make available a test crew for one day, at cost. No transport charges were incurred since the crew were not far from the area at the conclusion of a previous contract. The Conservators of Epping Forest generously agreed to finance this one day exploration, which took place on 9 April 1975. At this time Heronry Pond was filled completely, and for the first time in some years, the entire system was functioning as its designers had intended. Additional geological data has been made available by the Borough Engineer of Redbridge, so that in all, we have information from three boreholes sunk into the Taplow Gravel:
Page 26 shows the surface and sub-surface geology (in elevation) at the eastern end of Heronry Pond. From this it will be seen that there appears to be a substantial bed of gravel between the bottom of Heronry Pond, and the under-lying London Clay. The underlying clay appears to slope gently downwards in an easterly direction, from the point north of the East Island where it is exposed on the surface, to somewhere near the eastern edge of Heronry Pond, where at Albury Borehole No. 1 the clay is six metres below ground level. Since the bed of the pond is about 1.8 metres below ground level by Albury Borehole No. 1, this suggests that a layer of gravel stretches across Heronry Pond beneath its eastern end, about 4.2 metres thick. The underlying clay then appears to rise very gently further eastwards, beneath Perch Pond on its south side, across the valley. These findings are consistent with the geological survey map of 1921, and the geological "setting" of the lakes system. It seems quite likely that whilst the gravel beneath Perch Pond may be two or three metres thick at its western end, where the lake is shallow, this may diminish towards the eastern end where the lake is much deeper. In other words, the eastern end of Perch Pond appears likely to be bedded upon clay, but not the eastern end of Heronry Pond (or at least not the south-eastern corner of Heronry Pond). Details of the Albury Laboratories report are at Annex ll & III. (not available). From these it will be seen that a falling head permeability test was undertaken at Borehole No. 2. The method is described in Albury Laboratories letter CVS/MAJ/752 of 1 May 1975 (Annex II). (not available). The permeability of the granular soil, i.e. the Taplow Gravel, was found to be a value of:
It can be seen from the chart included with the Albury report that this order of permeability lies on the boundaries of good to poor drainage. We understand that when soil of any nature is disturbed, permeability is likely to be substantially increased, if no counter-measures are adopted. The result would be as if an "improved" route for seepage had been created, through the area of disturbed soi1. Conclusions of Exploration The above findings indicate that the initial cause of seepage from Heronry Pond probably lies in the form of construction at its eastern end, and specifically that the eastern embankment, between Heronry Pond and Perch Pond
It is not known whether these weaknesses in construction date from the original eighteenth century designs, or from the later remodelling (see below). However, so long as the inflow was sufficient to counter such weaknesses, there would be no problem. In drought years though, e.g. 1929, when inflow diminished, Heronry Pond water level would tend to fall during the summer months. One would also expect the pond water level to be sensitive to any significant disturbances to the adjacent terrace of Taplow Gravel, i.e. excavations. Finally,
in so far as the distribution of gravel may be uneven from place to place, the
determination of any more precise conclusions would be dependent upon establishment
of interface of the gravel and clay at many more locations in the area. Decline of the System and Heronry Pond Virtually any pond or lake leaks to some extent, or loses water through evaporation, or both. In this sense then, it is relevant to define precisely how such features are created. Our definition is that a lake or pond is created when there is a net surplus of inflow over outflow at some point, or when the two are in equilibrium. In other words, if water flows away from a point at a faster rate than it arrives at that point, then conditions are not conducive to the formation of a lake or pond. Thus to understand fluctuations in the water level of Heronry Pond, it is necessary to examine closely any factors likely to vary:
Furthermore, to the extent that Heronry Pond is simply one link in a chain of lakes, it is necessary to examine such changes not just to Heronry Pond, but to the overall system. Such an examination must start by asking the question: was the total inflow surplus to the total outflow from the time when the system came into existence? Two pointers suggest this was not the case. We have noted the ambitious designs drawn up by Jean Rocque in 1735, and how these differed from the map of 1745 which probably showed the reality of what was achieved (see page 14). It never proved possible to realise either of the grand designs for The Great Lake, which remained a rather irregular shape, reputedly very shallow, and by the time of its disappearance in about 1908, no more than a collection of marshy puddles. Secondly, it never proved possible to raise the level of Heronry Pond, or otherwise extend it westward, to join up with Shoulder of Mutton Pond. These two factors, plus the construction of a special artificial river - the "River Holt" - to tap a wider catchment area, suggest that it was realised by the mid-eighteenth century that the Rocque designs were over-ambitious. Furthermore, there is some evidence that difficulty was being encountered with Heronry Pond itself. In 1762, Jean Rocque was commissioned by Prince John, Duke of Montague, to produce a plan of London, which "just happened' to include in its north east corner, the park at Wanstead. This plan shows an embankment running north-south across Heronry Pond, about three-quarters of its length from the western end, and parallel with the embankment separating Heronry Pond with Perch Pond (see page 29) On such a small scale as this however (on a plan of the whole of London), such precise accuracy may be in question for eighteenth-century cartographers. However, Jean Rocque would have had a personal interest in ensuring that the features illustrated at Wanstead were reasonably accurate, bearing in mind his previous contact with the area. The purpose of such an embankment could very possibly have been to hold back the descent of water down into the Roding, as in the case of the other north-south embankments down the valley. If this was the case, it could be construed as showing that Heronry Pond was not, even at that time, maintaining its full level. On
another map, this time by Chapman and Andre (Plate XXI) and dated 1777, no "supplementary"
north-south embankments are shown along the length of Heronry Pond. Likewise on
an estate plan of the area following a survey in 1779, Heronry Pond is shown with
several large islands close to its south side, but with no additional north-south
embankments (see
page 31). Both these maps are available in the Essex Record Office, and our
attention was drawn to them by Mr J. Elsden Tuffs. Construction of this second embankment across Heronry Pond again suggests that attempts were being made to stop its water from draining away, eastwards, down into the valley of the Roding. Disappearance of The Reservoir in 1815 is a further pointer to the fact that even the extended catchment area of the system, as fed by the "River Holt", could not provide a satisfactory inflow. Naturally there would be fluctuations over time, due to the local weather conditions and particularly the rainfall, but we feel there are sufficient indicators to believe that there was a deficit balance between inflow and outflow, throughout the eighteenth century and into the early nineteenth century. Break-up of the Estate In the period 1822-24 the great house of Wanstead was demolished, and the main part of the grounds were closed and placed under the care of various game-keepers for the following sixty years. The Great Lake, containing its island with Lake House built upon it, was outside the closed area. The house was occupied by various families of renown, e.g. the author Thomas Hood, but it was deteriorating rapidly. It was also made the less attractive by the fact that its surrounding lake had, by the 1830's, dwindled to no more than ditches around the edge. * Here then, is further evidence that there was a deficiency in the inflow, with two of the top-most lakes of the system lost to all intents by the early nineteenth century. (The Great Lake was not properly filled-in until about 1908, when the site was acquired for property development, and the Lakehouse estate was built). * (See 'The Story of Wanstead & Woodford" pp 77, by J Elsden Tuffs). Between 1824 and 1880, there was very little change made to Heronry Pond - at least intended change. Much of its surrounding area was given over to rough grazing. The most significant event for the system occurred in the middle of the nineteenth century, in an apparently unrelated spot. The Eastern Counties Railway was opened in l843, and a branch line from Stratford - called the Woodford and Loughton Railway - started operating in 1856. As a consequence, the "River Holt" that had been channelled from Leytonstone Flats, down Spratt Hall Road, to The Basin, was severed in two by the railway cutting. Suddenly, a substantial part of the catchment area of the system, so painstakingly tapped by Adam Holt more than a century before, was completely isolated from the lakes of the park. As a result of the further deterioration of inflow of water into the lake system, and with the lack of proper care and maintenance to it because of its closure and the demolition of the great house, the facilities of the park were under pressure in the latter part of the nineteenth century. A six-inch Ordnance Survey map of the area, dated 1873-81, showed Heronry Pond only half its normal size, and with the entire western end no more than a marsh. Such was how the Conservators of Epping Forest found the pond in 1882, when the park came into the ownership of the Corporation of the City of London (see page 34). Not only that, but it was found that the previous tenant of the park had dug a ditch through the embankment between Heronry Pond and Perch Pond, in order to keep the former at a minimal level, and so increase his grazing areas The previous history of Heronry Pond makes it likely that the ditch in question was dug not to drain the pond - because we believe it tended to do that periodically with the weather in any case. The ditch was probably dug to prevent the lake from flooding - or reverting to its larger size - at times when there was a surplus of inflow over outflow. It was intended to keep the level down, rather than to get it down initially. Had the pond been full and stable at all times, it seems much less likely that such a ditch would have been dug, although this is speculation. One of the first acts of the Epping Forest Committee of the Corporation of London was to have the offending ditch filled in, thus restoring Heronry Pond to its original size. In the following year, 1883, the Committee came to an agreement with a Mr Chapman, for the boating rights covering both Heronry Pond and Perch Pond. This agreement lasted for many years. From 1883 until the end of
the century, the records show a number of complaints about the state of Heronry
Pond - primarily in 1893, 1896 and 1898. In 1893 Heronry Pond had "dried up considerably" by the end of the summer. In October of that year the Superintendent (of Epping Forest) reported that the low water level was due to the "exceptionally dry summer" and the fact that the water had washed away the retaining bank at the lower (eastern) end of the pond, and was easily able to drain through the gravelly soil remaining. The remedy adopted was to deepen the sides and strengthen the banks of the pond. In 1896, and again in 1898, Mr Chapman complained of loss of income from his boating rights, and asked that the pond should be "cleaned out." It is impossible to determine how much Mr Chapman's complaints concerned the condition of the water, as distinct from the lack of it, but certainly all was not well. 1900 - 1905 The drainage problem grew much worse from 1900. The Committee received public complaints about the low water level every year from 1900 to 1904, and it appears that the pond was dry every summer from 1900 to 1907. As a result, Mr Chapman's annual rent was reduced from £100 to £65 in 1900 and to £20 in 1901. The problem can be illustrated by two maps which appear in different editions of a booklet entitled "Epping Forest" by Edward North Buxton, and published by Edward Stanford. In early editions of the guide, Heronry Pond is shown in its largest area, as restored by the Epping Forest Committee in 1882 (see page 36). But in the seventh edition of the same guide, published in 1905, Heronry Pond (un-named) is shown in almost its pre-1882 condition - half size, eastern end only. Indeed, one might easily confuse the seventh edition (1905) map with others of thirty years before (e.g. the six inch 0rdnance Survey of 1873-81 - page 34), were it not for the Midland Railway line running through Leytonstone Station and Wanstead Park Station, (page 37). The railway runs across the bottom third of map, from left side). (see also Edwardian postcard view of the pond) At first, the huge deterioration of Heronry Pond was attributed to the dry summers of 1900, 1901, and 1902. However, after the wet summer of 1903, it was clear that some long-term factor(s) underlay the problem. In October 1903, the Superintendent reported that:
The
sewer in question was laid in 1900 to serve the Aldersbrook Estate, and runs within
a few yards of Heronry and Perch Ponds for most of their length, beneath Northumberland
Avenue. It should also be noted that most sewers of that period throughout Wanstead
were of the semi-segregated variety, such that rain falling on roads, footpaths,
and roofs of houses, ultimately found its way largely into the foul sewer pipes,
just as much as into the storm sewer system. When this occurred, the rainfall
was lost to the catchment area of the lake system - a further significant reduction
in inflow as the suburban development of Wanstead gradually progressed at the
turn of the century.
We have no reliable means of substantiating this report, and must take it at face value, bearing in mind that civil skills were well-developed by the turn of the century. However, the report makes no reference to the semi-segregated nature of the new sewer system, nor to weather conditions prior to the inspection, to indicate anything about the source of the clean water, apart from the adjacent lakes. When this sewer was excavated in 1977, there were differing reports about its soundness. It is therefore impossible to say whether or not groundwater was in the pipes inspected by Mr Lawford in 1903, or whether it was rainwater - with the groundwater finding its way along the line of the disturbed gravel of the sewer trench on the outside of the actual sewer pipe (see page 27 above). Mr Lawford suggested three solutions, in order of preference. First, having the sewer re-laid in cast iron to make it watertight, at a cost of £2,500. Second, constructing a puddle trench - three feet wide and carried down two feet into the London Clay bed - around both Heronry and Perch Ponds, at a cost of £2,200. Third, draining off the water and puddling the bottoms of Heronry and Perch Ponds, at a cost of £7,000. The immediate reaction of the Committee was to write to the local authorities surrounding Wanstead Park to ask "what sum they would be prepared to contribute on the basis of the work being carried out at a cost of £2,000." The local authorities denied responsibility, and by 1905 it was clear that they were also unwilling to make any kind of contribution to the estimated costs. The Superintendent therefore arranged a meeting between Mr Bailey Denton himself, and the engineers from the local authorities. According to the Superintendent, "the general consensus of the meeting was with Mr Bailey Denton "but there was apparently "little chance of getting contributions from the Councils," shortly after this meeting, Mr Bailey Denton prepared a second report in broad agreement with Mr Lawford's report. He pointed out that:
1906-1908 By 1906, the Committee had found the "ideal" solution - to have the necessary work carried out at minimal cost by unemployed men under the control of the West Ham Distress Committee. Most of the work was financed by the Local Government Board, although the Committee made a contribution of £500. The
work involved two main projects, neither of which appear to have been related
to any of the recommendations of the engineers previously consulted! The first
project, in 1906, was designed to increase inflow. The second, in 1907, was aimed
at decreasing outflow. 1909 - 1940 For the next thirty years,
there was not a single complaint about the condition of Heronry Pond, although
in 1929, Mr Chapman had his rent reduced, following the "excessive drought"
in the summer of that year. During the Second World War, the lake system
of Wanstead Park suffered calamitous damage, which substantially affected both
outflow and inflow - although the latter's significance has never been fully appreciated
until now.
Records
indicate that high explosive bombs ranged from 250 lbs to 2,000 lbs. Land mines
consisted of approximately one ton of high explosive, capable of causing blast
effects up to 650 yards from the point of explosion. The VI flying bomb consisted
of approximately 1,000 lbs of high explosive. Unfortunately, so long after these contracts, W & C French cannot locate any papers relating to the works which might indicate either old or new construction details, nor do they have anybody in their employ who was concerned with the work. 1950 - 1958 In February 1952, the Superintendent reported that the repairs to Heronry Pond had not solved the seepage problem:
The Committee asked him
to organise weekly readings of the water level, and report back in twelve months.
In
the winter of 1953/54, the pond was drained and the Wanstead Park staff carried
out repairs to all noticeable defects in the concrete base, in an attempt to seal
leaks, Then, between July 1954 and October 1955, monthly readings were taken of
the depth of the pond (see
middle diagram - page 46). Comparison with the 1952/53 readings demonstrated
that the repairs had not reduced seepage. 1974 - 1978 In 1974, the Conservators of Epping
Forest were approached by contractors seeking locations for the disposal of spoil,
with a view to filling Heronry Pond. However, it was pointed out
by those interested in a more positive solution, that there was no guarantee that
filling one third of the pond would necessarily result in the remaining two thirds
suddenly achieving a stable water level. Furthermore, since the pond had a very
long and significant history, and formed a central link in the chain of remaining
lakes which would otherwise be broken, the opportunity should be given to carry
out a further investigation to determine the basic problem, and to propose a solution
if possible.
-
so that no progress was made in the direction of saving Heronry Pond either! Relaying of Northumberland Avenue Sewers (1977) During
1977, Northumberland Avenue was excavated along its entire length, and the sewer
system laid in 1900 was completely replaced. The works were continued along the
complete length of Woodlands Avenue during the winter of 1977/8. In addition, it will be noticed that
the level of the new foul sewer is below the level of the bed of Perch Pond at
its western end, whereas the old foul sewer was very nearly on the same level
as the bed of the lake at this point. Such additional disturbance of the Taplow
Gravel almost one metre deeper than before, could lead to problems of maintaining
water level stability in Perch Pond, of a similar kind to those which have plagued
Heronry Pond for the past years. However, there is no evidence of this to date.
(See also Part 1 - The Lake System of Wanstead Park by James Berry & Alan Cornish) (See also Wanstead Watercourses: the "River Holt" by Barry Hughes) (See also The City of London Cemetery/Ponds) |
|||||||||||
|
|||||||||||